Scope of work

  • Construction of watchtower, fire-fighting building, technical blocks, runway, apron and some sections of the airport landscape.

Main Figures

  • Asphalt
  • Concrete
  • Reinforcement
  • Steel Structure
  • Formwork
  • Landscaping
100,000 ton
45,000 m³
2500 ton
80 ton
140,000 m²
80,000 m²

Achievements

  • Due to superior performance, the initial scope of work was extended by three more contracts.

Comments

  • Fire-fighting building
    • State-of-the-art facilities and equipment in control room enable operators to monitor the key locations in real time.
  • Control tower
    • The 35 meter high tower has two main stories for flight control and navigation equipment.
    • Utilizing the sliding formwork method, the main tower was constructed just in 9 days.